You can have only one task at the top level of the task hierarchy in the Project Manager tool or in the Task Manager tool in Groove (922134)
The information in this article applies to:
- Groove Virtual Office 3.1 Professional Edition
- Groove Virtual Office 3.1 Project Edition
- Groove Virtual Office 3.0 Professional Edition
- Groove Virtual Office 3.0 Project Edition
- Groove Workspace 2.5 Professional Edition
- Groove Workspace 2.5 Project Edition
INTRODUCTION
This article discusses the fact that you can have only one task at the top level
of the task hierarchy in the Project Manager tool or in the Task Manager
tool in Groove Workspace and in Groove Virtual Office.MORE INFORMATIONThe first task that is created in the Project Manager tool
or in the Task Manager tool should describe the defining task for the whole
project. This task always resides at the top of the task hierarchy. After
the first task is entered, you can enter any number of second-level tasks. However, you cannot add a second top-level task.
If you have another task that
is truly hierarchically equal to the defining project task, that task is another
project. Therefore, that task requires its own Project tool and
tab.
Modification Type: | Major | Last Reviewed: | 7/6/2006 |
---|
Keywords: | kbhowto kbExpertiseInter KB922134 kbAudKnowledgeWorker kbAudEndUser |
---|
|