Outline code values that are assigned to tasks or resources are missing after you edit a lookup table in Microsoft Project (321664)
The information in this article applies to:
- Microsoft Project Standard 2002
- Microsoft Project Professional 2002
This article was previously published under Q321664 SYMPTOMS
In Microsoft Project, after you cut and paste, or copy and paste, custom outline code entries in a lookup table, the outline code values that were previously assigned to existing tasks or resources may be missing.
For example, after you cut and paste entries in a lookup table that contains task outline code information, the outline code values that were assigned to existing tasks in your project no longer appear in Gantt Chart view.
The custom outline codes can be any of the following:
- Task or resource outline codes (in Microsoft Project Standard and Microsoft Project Professional)
- Enterprise task, resource, or project outline codes (in Microsoft Project Professional)
RESOLUTION
To work around this problem, reenter the outline code value that you want to assign to the field for the task or resource, as appropriate.
STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article. MORE INFORMATIONFor more information about lookup tables and outline codes in Microsoft Project, click Microsoft Project Help on the
Help menu, type lookup table in the Office Assistant or
the Answer Wizard, and then click Search to view the topics
returned.
Modification Type: | Minor | Last Reviewed: | 1/7/2006 |
---|
Keywords: | kbtable kbpending KB321664 |
---|
|