PRJ2000: Rounding Errors Occur When You Enter Data in Task Usage View (242683)
The information in this article applies to:
This article was previously published under Q242683 SYMPTOMS
When you enter values into work timescales in Task Usage view, Microsoft Project rounds values to the next highest or lowest increment.
CAUSE
Microsoft Project uses a set level of precision when evaluating work timescale values entered in hour units. Work values that are precise to one one-hundredth of an hour may be automatically incremented or decremented by one one-hundredth. This is so that Microsoft Project can complete related computations.
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbbug KB242683 |
---|
|