How to create a Gantt chart using hours as the scale (213915)
The information in this article applies to:
- Microsoft Office Excel 2003
- Microsoft Excel 2002
- Microsoft Excel 2000
This article was previously published under Q213915 For a Microsoft Excel 98 and Excel 97 version of this
article, see
152820. SUMMARY You can use a Gantt chart to show the progress of a project
or the relationship among the tasks in a project in relation to time. The unit
of time that is most frequently used is the day unit. However, you can also use
the hour as the unit of time to show the status of the task. To do this in
Microsoft Excel, alter the scale of the value (y) axis.
This article
contains an example that uses the hour as the unit of time to show the status
of a task.REFERENCES For more
information about creating charts, click Microsoft Excel Help
on the Help menu, type create a chart
in the Office Assistant or the Answer Wizard, and then click
Search to view the topic.