PRJ: Task Outline Numbers Incorrect After Sorting (196148)
The information in this article applies to:
- Microsoft Project 2000
- Microsoft Project 98 for Windows
This article was previously published under Q196148 SYMPTOMS
In Microsoft Project, when you sort a project, the task outline numbers
may not update to reflect the correct new outline numbers.
CAUSE
This problem may occur when you sort a project in a task view and the
Permanently Renumber Tasks option is selected (on the Project menu, point at Sort and then click Sort By).
WORKAROUND
To work around this behavior, follow these steps:
- Select task 1.
- On the Project menu, point to Outline, and then click
Indent.
The outline numbers update to display the correct outline numbering
sequence.
STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.
Modification Type: | Major | Last Reviewed: | 10/7/2003 |
---|
Keywords: | kbbug kbpending KB196148 |
---|
|