PRJ: Milestone Task Has Incorrect Finish (195524)
The information in this article applies to:
- Microsoft Project 2000
- Microsoft Project 98 for Windows
This article was previously published under Q195524 SYMPTOMS
In Microsoft Project, a task marked as a milestone or a task with zero
duration may have an incorrect finish date.
NOTE: This behavior may also affect Summary tasks' finish dates and the scheduling of successors of that task.
CAUSE
This behavior may occur when you do the following:
- In the Gantt Chart, you click the blank region to the left of a
milestone, and drag left in order to create a task on the same row
as the milestone.
This behavior occurs with the following types of tasks:
- Tasks with a duration of 0 (zero) days.
- Tasks marked as a milestone.
WORKAROUND
To work around this behavior, use the appropriate method for your situation.
Method 1: If the duration of the milestone is 0 days, increase the duration
of the milestone to 1d. Then, reedit the milestone's duration back to 0d.
Method 2: If the duration of the milestone is greater than 0 days, reduce
the duration to the correct value.
STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.
Modification Type: | Major | Last Reviewed: | 10/7/2003 |
---|
Keywords: | kbbug kbpending KB195524 |
---|
|