Unfinished Scheduled Tasks Are Incorrectly Listed as Finished (188233)
The information in this article applies to:
This article was previously published under Q188233 SYMPTOMS
When you view the Task Scheduler tool, the Last Run Time column may
indicate that a scheduled task has completed even though the task has not
completed.
CAUSE
This behavior can occur for either of the following reasons:
- Two tasks are scheduled to start at the same time.
- A task is scheduled to start while another task is still running.
RESOLUTION
To resolve this issue, change the scheduled start time of one of the
conflicting tasks so that only one task is run at a time. For information
about how to do so, click Start, click Help, click the Index tab, type
task scheduler, and then double-click the
Modifying Tasks topic.
Modification Type: | Minor | Last Reviewed: | 12/16/2004 |
---|
Keywords: | kbprb kbui KB188233 |
---|
|