PRJ98: Crash If Selecting Calendar in Change Working Time Dialog (185877)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q185877 SYMPTOMS
In Microsoft Project 98, when you select a calendar in the Change Working
Time dialog box, you may receive one of the following error messages.
In Windows 95
This program has performed an illegal operation and will be shut down.
If the problem persists, contact the program vendor.
When you click Details, you receive the following error:
WINPROJ caused an invalid page fault in module WINPROJ.EXE at <address>.
In Windows NT
An application error has occurred and an application error log is being generated.
WINPROJ.EXE
Exception: access violation <number>, Address: <address>.
CAUSE
This behavior occurs in consolidated projects when you do the following in
the Change Working Time dialog box:
- You choose any custom (nonstandard) calendar from an inserted
project.
- You choose a second calendar that has not yet been used in the
consolidated project.
RESOLUTION
To correct this problem, install Microsoft Project 98 for Windows Service
Release 1 (SR-1).
To work around this problem in Microsoft Project 98 (non SR-1), follow
these steps:
- On the Tools menu, click Organizer.
- Click the Calendars tab.
- Select any calendars in the Global.mpt that are not already in your
project.
- Click Copy.
- Click Close.
STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, click the
article number below to view the article in the Microsoft Knowledge Base:
185102
PRJ98: How to Obtain and Install MS Project 98 SR-1
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbbug kberrmsg KB185877 |
---|
|