PRJ98: Total Cost Different from Edited Timephased Actual Cost (185484)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q185484 SYMPTOMS
In Microsoft Project 98, when you edit timephased assignment Actual Cost for a task that is in-progress, you may see a different value in the Total Cost field when compared to the total of the timephased cost.
CAUSE
This behavior may occur when following conditions are true:
- The Actual costs are always calculated by Microsoft
Project check box is clear. To locate this option, on the
Tools menu click Options, and then click the
Calculations tab.
- You manually enter timephased actual cost data for an in-progress
task that has a resource with a Cost Per Use assigned to
it.
WORKAROUND
To correct this problem, install Microsoft Project 98 for Windows Service
Release 1 (SR-1).
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, click the
article number below to view the article in the Microsoft Knowledge Base:
185102
PRJ98: How to Obtain and Install MS Project 98 SR-1
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbbug KB185484 |
---|
|