PRJ98: Flashing Screen or Endless Alert When Linking Tasks (184612)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q184612 SYMPTOMS
In Microsoft Project 98, in a consolidated project, when you link from a
summary task in one inserted project to a task in a second inserted
project, you may receive any of the following behaviors:
- The screen may begin to flash endlessly.
- You may receive a scheduling message that repeats endlessly.
- The word "calculate" appears at the bottom of the screen. (This
behavior occurs when Calculation is set to Manual.)
CAUSE
This behavior occurs when the following conditions are true:
- You have a consolidated project that contains at least two inserted
projects.
- One inserted project is scheduled From Finish.
- A second inserted project is scheduled From Start.
- In the consolidated project, you link the summary task in the first
inserted project (scheduled From Finish), to a task in the second
inserted project (scheduled From Start).
WORKAROUND
Remove the link between the summary task the in first inserted project and
the task in the second inserted project.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, click the
article number below to view the article in the Microsoft Knowledge Base:
185102
PRJ98: How to Obtain and Install MS Project 98 SR-1
MORE INFORMATION
The screen flashes because Microsoft Project is calculating in an endless
loop.
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbbug KB184612 |
---|
|