OL98: Day Missing in Noncontiguous Work Week Selection (182459)
The information in this article applies to:
This article was previously published under Q182459 SYMPTOMS
After defining a noncontiguous work week in Microsoft Outlook 98, the last
day of that week will not be visible in Work Week view.
RESOLUTION
Add one additional day to the end of the work week. This will cause your
Work Week calendar to display properly.
STATUS
Microsoft has confirmed this to be a problem in Microsoft Outlook 98.
We are researching this problem and will post new information here in the
Microsoft Knowledge Base as it becomes available.
Modification Type: | Major | Last Reviewed: | 1/27/2000 |
---|