PRJ: Unexpected Values in Cost, Actual Cost, or Remaining Cost (180295)
The information in this article applies to:
- Microsoft Project 2000
- Microsoft Project 98 for Windows
This article was previously published under Q180295 SYMPTOMS
In Microsoft Project, you may find unexpected task costs in the Cost,
Actual Cost, and Remaining Cost fields.
CAUSE
This problem occurs when the following conditions are true:
- You set the Cost (Total Cost) for the task to zero.
- The option "Actual costs are always calculated by Microsoft Project"
is turned off.
- The task is between 0 and 100 percent complete.
WORKAROUND
To work around this problem, allow Microsoft Project to calculate Actual
Costs by following these steps:
- On the Tools menu, click Options.
- On the Calculation tab, click to select the Actual costs are always calculated by Microsoft
Project check box.
- Click OK.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
Modification Type: | Major | Last Reviewed: | 10/7/2003 |
---|
Keywords: | kbbug kbpending KB180295 |
---|
|