PRJ98: Entering a Cost for a Resource Assignment Results in Zero (179790)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q179790 SYMPTOMS
In Microsoft Project 98, when you enter a cost for a resource assignment,
it may revert back to zero.
CAUSE
This problem occurs when the following conditions are true:
- The task you are assigning the cost to has a resource assigned at
zero units, or the resource has zero work for the task.
- The option for Actual Costs are Always Calculated by
Microsoft Project is turned off.
WORKAROUND
To work around this behavior, use the method appropriate for your
situation:
- If you have not assigned any actual costs to the project, turn on
the Actual Costs are Always Calculated by
Microsoft Project option, assign the Cost, and then turn
off the Actual Costs are Always Calculated by
Microsoft Project option. (To set the Actual
Costs are Always Calculated by Microsoft Project option, click
Options on the Tools menu, and then click the
Calculation tab.)
NOTE: If you turn the Actual Costs are Always
Calculated by Microsoft Project option back on, all actual costs
are lost.
- If you have assigned actual costs to the project, you must assign
the cost to the task as an Actual Cost when the task is
completed.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, click the
article number below to view the article in the Microsoft Knowledge Base:
185102
PRJ98: How to Obtain and Install MS Project 98 SR-1
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbbug KB179790 |
---|
|