PRJ: Removing All Resources From Task Removes All Work (178185)
The information in this article applies to:
- Microsoft Project 98 for Windows
- Microsoft Project for Windows 95 4.1
- Microsoft Project for Windows 95 4.1a
- Microsoft Project for Windows 4.0
- Microsoft Project for the Macintosh 4.0
This article was previously published under Q178185 SYMPTOMS
In Microsoft Project, if you remove all resources from a task, the Work
assigned to the task is also removed.
Although you might expect that a Fixed Work task would not lose assigned
work when a resource is removed, this behavior occurs for all types of
tasks: Fixed Work, Fixed Duration, and Fixed Units.
WORKAROUND
To work around this problem, reassign the value of Work to the task after
removing all the task's resources.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, click the
article number below to view the article in the Microsoft Knowledge Base:
185102
PRJ98: How to Obtain and Install MS Project 98 SR-1
Modification Type: | Major | Last Reviewed: | 11/25/2003 |
---|
Keywords: | kbbug kbpending KB178185 |
---|
|