PRJ98: Error Sending TeamStatus Message for Summary Task (176289)



The information in this article applies to:

  • Microsoft Project 98 for Windows
  • Microsoft Project for Windows 95 4.1
  • Microsoft Project for Windows 95 4.1a

This article was previously published under Q176289

SYMPTOMS

In Microsoft Project, if you send a TeamStatus message for an entire project, summary tasks will not be included in the message. In addition, if you attempt to send a TeamStatus message for a selected summary task, you will receive the following error message:
There are no valid tasks selected.

Try one of the following:

-Select a different task(s), and then try again.

-Make sure that the resource assigned to the task doesn't have a workgroup setting set to None on the General tab of the Resource Information dialog box.

WORKAROUND

To work around this problem, send a TeamStatus message for each individual task under the summary task.

STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

Modification Type:MajorLast Reviewed:10/7/2003
Keywords:kbbug kberrmsg kbinterop kbpending KB176289