PRJ98: Error Sending TeamStatus Message for Summary Task (176289)
The information in this article applies to:
- Microsoft Project 98 for Windows
- Microsoft Project for Windows 95 4.1
- Microsoft Project for Windows 95 4.1a
This article was previously published under Q176289 SYMPTOMS
In Microsoft Project, if you send a TeamStatus message for an entire project, summary tasks will not be included in the message. In addition, if you attempt to send a TeamStatus message for a selected summary task, you will receive the following error message:
There are no valid tasks selected.
Try one of the following:
-Select a different task(s), and then try again.
-Make sure that the resource assigned to the task doesn't have a
workgroup setting set to None on the General tab of the Resource
Information dialog box.
WORKAROUND
To work around this problem, send a TeamStatus message for each individual task under the summary task.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
Modification Type: | Major | Last Reviewed: | 10/7/2003 |
---|
Keywords: | kbbug kberrmsg kbinterop kbpending KB176289 |
---|
|