PRJ98: Incorrect Work Value in Usage Views for In-Progress Tasks (175031)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q175031 SYMPTOMS
In Microsoft Project 98, the Task Usage and Resource Usage views may show incorrect Work and Actual Work values for some tasks and resources when the task is in progress.
CAUSE
This behavior occurs when the following conditions occur:
- You are using a resource pool and the start date of the resource
pool is later than one or more of the project files sharing the
pool. This causes Microsoft Project to calculate task usage and
resource usage incorrectly for a task that is in progress.
- You created a new default calendar exception for a day of the week
for a resource or base calendar. For example, you made Monday a
nonworking day. For a past date on which actual work was done, the
working time will be incorrect.
WORKAROUND
To work around this problem, change the project start date for the resource
pool so that it is the same as the project's sharing pool. To do this,
follow these steps:
- On the Tools menu, click Change Working Time.
- In the For list, select the calendar you modified.
- Click the day title you changed previously.
- Under For Selected Dates, click Use Default, and then
click OK.
- On the Window menu, click the resource pool.
- On the Project menu, click Project Information.
- In the Start Date box, enter the start date of the earliest
project.
- Click OK.
- Re-enter the calendar exception.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, click the
article number below to view the article in the Microsoft Knowledge Base:
185102
PRJ98: How to Obtain and Install MS Project 98 SR-1
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbbug kbusage KB175031 |
---|
|