PRJ: % Complete Not Updated for Inserted Projects (171396)
The information in this article applies to:
- Microsoft Project 2000
- Microsoft Project 98 for Windows
This article was previously published under Q171396 SYMPTOMS
When you attempt to update the Percent Complete for a project, inserted projects will not be updated.
WORKAROUND
To work around this problem, edit the inserted project and set the correct
Percent Complete value for the Summary task.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
Modification Type: | Major | Last Reviewed: | 11/4/2003 |
---|
Keywords: | kbprb kbusage KB171396 |
---|
|