PRJ: Task Split Information Not Saved When Using Work Contour (171394)



The information in this article applies to:

  • Microsoft Project 2000
  • Microsoft Project 98 for Windows

This article was previously published under Q171394

SYMPTOMS

When you change the contour of a resource assignment, task split information is not preserved.

CAUSE

Microsoft Project does not track task split information if a contour is chosen for a task.

STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

Modification Type:MajorLast Reviewed:11/4/2003
Keywords:kbprb kbusage KB171394