PRJ: Task Split Information Not Saved When Using Work Contour (171394)
The information in this article applies to:
- Microsoft Project 2000
- Microsoft Project 98 for Windows
This article was previously published under Q171394 SYMPTOMS
When you change the contour of a resource assignment, task split information is not preserved.
CAUSE
Microsoft Project does not track task split information if a contour is
chosen for a task.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.