TMGR: Unexpected Total Work for Recurring Task Properties (167970)



The information in this article applies to:

  • Microsoft Team Manager

This article was previously published under Q167970

SUMMARY

In Team Manager, Task properties for a recurring task will reflect a different value of Total Work than what is shown in the Total Work field in any view.

MORE INFORMATION

Recurring Task Properties reflects the value of Total Work that the first task of the recurring task set shows as a value of Total Work, not the value of the recurring task itself. For example, a recurring task made of three one day tasks would reflect three days of Total Work. But in Recurring Task Properties, a value of one day would be shown.

Modification Type:MinorLast Reviewed:8/17/2005
Keywords:KB167970