TMGR: Removing Actuals Sets Status to In Progress (161822)
The information in this article applies to:
This article was previously published under Q161822 SYMPTOMS
If an assignment has non-zero Actual Work, then clearing all the Actual
Work sets the assignment Status to In Progress.
This behavior occurs regardless of the original Status of the assignment,
but is incorrect if the original Status was "Waiting on someone else" or
Deferred.
WORKAROUND
From the Status field for the assignment, reselect the desired value.
STATUS
Microsoft has confirmed this to be a problem in Microsoft Team Manager 97.
We are researching this problem and will post more information here in the
Microsoft Knowledge Base as it becomes available.
Modification Type: | Minor | Last Reviewed: | 8/17/2005 |
---|
Keywords: | KB161822 |
---|
|