TMGR: Reschedule From Date Is One Day Later Than Chosen (161787)
The information in this article applies to:
This article was previously published under Q161787 SYMPTOMS
After using the Reschedule From command on the Tools menu, the date in the
Schedule From field for a person is one day later than the "Remaining work
should start on or after" reschedule date specified in the Reschedule From
dialog. Also, any remaining work that the person has on working days prior
to or on the specified reschedule date is converted to actual work.
This happens if a person has remaining work on working days prior to, or on
the specified reschedule date in the Reschedule From dialog, and the
"Assume work scheduled prior to the new start date is done" option is
selected.
WORKAROUND
The first topic below explains how to repair incorrect actual work that the
Reschedule From command may have entered. The second topic explains how to
use the Reschedule From command to mark actuals as desired.
Repairing Incorrect Actuals
The Edit Undo command can not be used to undo the results of the Reschedule
From command. If the Reschedule From command has incorrectly entered actual
work for a person up to and including the day that the person's remaining
work should start, then manually correct those actuals as follows: - Click the Tasks tab, and from the view banner dropdown list,
select Actual Work.
- Near the upper right corner of the window, move the timescale
slider to the leftmost position to format the timescale for
weeks over days.
- For each task that the person works on, double click the task folder
icon in front of the task name to display the assignment rows.
- In the grid under the timescale, for each of the person's assignments
and for each day prior to the reschedule date, enter the correct
actual work or delete it if there is none. Delete the actual
work on the reschedule date.
The person's Schedule From field in the People tab Profile Information view
should now show the correct Schedule From date.
Using Reschedule From to Mark Actuals
In the Reschedule From dialog, when using the option to mark prior work as
done, enter a date that is one day earlier than the date that remaining
work is really to begin. This is done as follows: - On the Tools menu, click Reschedule From.
- To reschedule specific people, in the For These People dropdown
list, click All People to deselect it, and then click the person(s)
to be rescheduled. (Skip this step if rescheduling all people).
- Click "Assume work scheduled prior to the new start date
is done" to select it.
- In the Reschedule From dialog box click the arrow by "Remaining work
should start on or after",and choose a date that is one day
earlier than the day that the person(s) should really begin remaining
work.
STATUS
Microsoft has confirmed this to be a problem in Microsoft Team Manager 97.
We are researching this problem and will post more information here in the
Microsoft Knowledge Base as it becomes available.
MORE INFORMATION
The Schedule From date for a person is always at least one day after the
last day containing actual work for the person, and remaining work is
scheduled on or after the Schedule From date. To view the Schedule From
field, click the People Tab and from the View Banner, select Profile
Information and select the person in the left pane.
The Reschedule From command can be used to change the Schedule From date
for all or specified people, but you cannot change it to a date that is on
or before the last day a person has actual work. To use the Reschedule From
command, on the Tools menu click Reschedule From.
NOTE: After using the For These People dropdown list, the "Remaining work
should start on or after" reschedule date may need to be reseleted.
If the "Assume work scheduled prior to the new start date is done" option
is selected and the person has remaining work, then the person's Schedule
From field is incorrectly set to a day later than the specified reschedule
date. Scheduled work is converted to actual work on working days up to and
including the specified date, rather than before it.
Modification Type: | Minor | Last Reviewed: | 8/17/2005 |
---|
Keywords: | KB161787 |
---|
|