TMGR: Default Work Unit Converts Pasted Number in Timesheet (161618)



The information in this article applies to:

  • Microsoft Team Manager

This article was previously published under Q161618

SYMPTOMS

If you copy and paste a number without a work unit (h, d, w, or m) into a cell in a timescaled grid in a timesheet view, such as the Actual Work view, the number is incorrectly interpreted as including the "Default work unit for new tasks" specified in the Options Work tab. The hourly conversion settings in the Options Work tab are then used to convert the pasted number and work unit to the corresponding value and current timescaled grid work unit (h, d, or w).

For example, suppose the "Default work unit for new tasks" is days, the Actual Work view timescaled grid is currently formatted to display work in hours, and the Options Work tab has "One work day is 8 hours." If you paste the number 10 into a cell in the timescaled grid, it will display 80h. This happens because the 10 is first treated as 10d (using "Default work unit for new tasks") and then converted to 80h (using "One work day is 8 hours").

NOTE: Manually entering 10 without a work unit results in 10h, because it correctly uses the current timescaled grid work unit instead of the "Default work unit for new tasks."

WORKAROUND

To ensure the proper interpretation of pasted work values, include the unit symbol h, d, w, or m with the numbers in the source document that the values are being copied from.

STATUS

Microsoft has confirmed this to be a problem in the products listed at the beginning of this article. We are researching this problem and will post new information here in the Microsoft Knowledge Base as it becomes available.

MORE INFORMATION

The work units h, d, w, and m stand for hours, days, weeks, and months, respectively.

Timesheet views, such as the Actual Work view, allow data to be entered in cells in a timescaled grid in the Actual Work, Actual Overtime Work, and Actual Standard Rate Work timesheet columns. To change which timesheet columns are displayed, on the Format menu, click Add/Remove Timesheet Columns.

Timesheet views can have an Upper and Lower timescale, or just an Upper timescale. Timescale Units (Days, Weeks, and so on) can be specified for the Upper and Lower timescales. To format the timescale, on the Format menu click Timescale, or use the timescale slider control near the upper-right corner of the window. The timescale slider choices of Daily, Weekly, Biweekly, Semimonthly, Monthly, or Quarterly are converted into appropriate settings in the Format Timescale dialog box.

The same work unit is used in all cells in a timesheet timescaled grid, and that work unit is determined by the Lower timescale Unit if both timescales are displayed, or the Upper timescale Unit if only one timescale is displayed. The table below shows the relationship between the timescale Unit and the timescaled grid work unit.
   Timescale Unit      Timescaled Grid Work Unit
   --------------      -------------------------
   Days                h
   Weeks               d
   Semi-Monthly        d
   Months              d
   Quarters            w
   Years               w
				
The "Default work unit for new tasks" setting in the Options Work tab has no effect on the timescaled grid work units.

Modification Type:MinorLast Reviewed:8/17/2005
Keywords:KB161618