TMGR: Dragging Task in Work Calendar May Cause Overload (161317)



The information in this article applies to:

  • Microsoft Team Manager

This article was previously published under Q161317

SYMPTOMS

You drag a task in the Work Calendar view, and when you view the task in a view such as the Task Organizer, it appears with as an overloaded task.

CAUSE

If you are in the Work Calendar view and the view is formatted for a weekly view, dragging a task to another week applies a Start Exactly on constraint to the task. The constraint is always the first date in the period, which happens to be Sunday. Sunday is typically a non-working day.

RESOLUTION

Change the constraint on the task to a working day. To do this, click Task Properties on the Edit menu, click the Scheduling tab, and change the Exactly On constraint to a working day.

STATUS

Microsoft has confirmed this to be a problem in the products listed at the beginning of this article. We are researching this problem and will post new information here in the Microsoft Knowledge Base as it becomes available.

Modification Type:MinorLast Reviewed:8/17/2005