TMGR: Summary Fields Show N/A or #Too Large# (159397)



The information in this article applies to:

  • Microsoft Team Manager

This article was previously published under Q159397

SYMPTOMS

Summary level tasks show N/A in fields such as Total Work, or show #Too Large# in fields such as Total Cost.

CAUSE

Microsoft Team Manager displays N/A or #Too Large# when a rolled-up field has exceeded the numerical capacities for the field.

The capacity of a rolled-up work-type field is:
     2,236,962.1 hours
				
The capacity of a rolled-up cost-type field is:
     $922,337,203,685.477.58
				

STATUS

This behavior is by design in Microsoft Team Manager.