TMGR: BCWP on Summary Task Incorrect If Grouped By People (147218)
The information in this article applies to:
This article was previously published under Q147218 SYMPTOMS
In a Task view, the BCWP (Budgeted Cost of Work Performed) on a summary
task appears incorrect if a subtask has two people assigned who have
different actual work and the view is Grouped By People.
CAUSE
When any Task view is grouped using Grouped By People, the summary task
is repeated for each person assigned to the subtasks and is not
recalculated. The Summary task's BCWP will display the same way for each of
subtasks. The BCWP (Budgeted Cost of Work Performed) is calculated based on
Percent Complete (for the ungrouped summary) multiplied by the Baseline
Cost (for the ungrouped summary).
Modification Type: | Minor | Last Reviewed: | 8/17/2005 |
---|
Keywords: | KB147218 |
---|
|