Import Project with Same Name as Existing Project Merges Tasks (146282)
The information in this article applies to:
- Microsoft Schedule+ for Windows 95
This article was previously published under Q146282 SYMPTOMS
When you import data into Schedule+ version 7.0, the tasks associated with
a project that currently exists in the schedule will be merged with those
associated with the project. If the imported task has the same name as an
existing task, the information in the task being imported will overwrite
the existing task information.
CAUSE
This is by design.
The ObjectID's for the individual objects are not exported to the .SCH file
during the export process. This eliminates duplication of ObjectID
conflicts between the two user's appointment books. The New ObjectID's for
the Projects or Tasks will be assigned when the user's appointment book is
imported.
In the case where a duplicate Project or Tasks name is found in the
destination appointment book, the imported Project or Tasks will assume the
ObjectID of the existing Project; therefore, it adds the
Same_Name_Project/Tasks from the exported file as part of the existing
Project in the appointment book.
Modification Type: | Minor | Last Reviewed: | 8/18/2005 |
---|
Keywords: | KB146282 |
---|
|