How to change working time in Project (143254)
The information in this article applies to:
- Microsoft Project 98 for Windows
- Microsoft Project for Windows 95 4.1
- Microsoft Project for Windows 95 4.1a
- Microsoft Project for Windows 4.0
- Microsoft Project for the Macintosh 4.0
- Microsoft Project 2000
- Microsoft Project 2002
- Microsoft Office Project Professional 2003
- Microsoft Office Project Standard 2003
This article was previously published under Q143254 SUMMARY This article includes information about changing the
working time of the Microsoft Project Standard calendar. This information also
applies to changing an individual resource calendar or creating a shift
calendar from a copy of the standard. MORE INFORMATION In Microsoft Project, there are three different types of
calendars. Before you modify a calendar, it important to consider what each of
these calendars does. The following information should familiarize you with each
of these types of calendars. The Project Calendar The project calendar defines basic scheduling properties for
tasks. To find out which calendar is the Project Calendar or to assign a
calendar, do the following: - Microsoft Project 98,
Microsoft Project 2000,?Microsoft Project 2002, and Microsoft Office Project 2003
On the Project menu, click Project Information.
In the Project
Information dialog box, the Calendar field contains the name of the calendar
that Microsoft Project is using as the file's main calendar. - Microsoft Project 4.1
On the File menu, click
Project Info.
In the Project Info dialog box, the Calendar field
contains the name of the calendar that Microsoft Project is using as the file's
main calendar. - Microsoft Project 4.0
On the File menu, click
Summary Info.
In the Summary Info dialog box, the Calendar field
contains the name of the calendar that Microsoft Project is using as the file's
main calendar.
Base Calendar You can use a base calendar or shift calendar to define alternate
available time schedules. The Project calendar (above) is always one of the
Base Calendars. The base calendars can also act as templates for
resource calendars. To find out what base calendar a resource is using, do the
following: - Microsoft Project 98
- On the View Menu, click Resource Sheet.
- On the Insert menu, click Resource
Information.
- Click the Working Time Tab.
The Base Cal field contains the name of the base calendar.
- Microsoft Project 4.0, Microsoft Project
4.1,
Microsoft Project 2000,?Microsoft Project 2002, and Project?2003
- On the View Menu, click Resource Sheet.
- On the Insert menu, click Resource
Information.
The Base Cal field contains the name of the base calendar.
Resource Calendar A resource calendar is a schedule of availability for an
individual resource. When a resource is created, Microsoft Project
automatically creates a calendar based upon the Standard base calendar. This
individual calendar only affects the resource's availability and is not used to
calculate the work for the resource. Moreover, a resource calendar
is an exception to the project calendar. Therefore, if a task is scheduled for
a time that a resource cannot work and the task is using resource-driven
scheduling, the task is adjusted (in many cases the finish date is adjusted) to
allow for the differences between the project calendar and the resource's
individual calendar. To change or view a resource's calendar, do the
following: - On the Tools Menu, click Change Working Time.
- In the For list, click the resource's name.
You
will now see the resource's individual calendar.
Calendar Options Microsoft Project makes a number of calendar options available.
To see these options, do the following: - On the Tools Menu, click Options.
- In the Options dialog box, click the Calendar tab.
These options do not change calendars or availability schedules
(as described above), but are simply definitions for specific defaults and
values for units. For brief explanations of some of these options, see the
following information: - Default Start Time/Default End Time
This option
defines the default time that is placed upon any Start Date or Finish Date in
which the user did not specify a time. Any fully qualified date includes month,
day, year, and time.
For example, if you set the Default Start Time
to 8:00 AM and you were to create a task that started 1/25/96, if you told
Microsoft Project nothing else, Microsoft Project still requires a time value
for the date entry. Because Default Start Time is set to 8:00 AM, this is the
time that will be added to the date you typed in. The fully qualified date for
the task would then be 1/25/96 at 8:00 AM. - Hours Per Day
This option defines the day unit to
be a certain number of hours. This option is important because the day unit
itself is not a concrete number in many business applications. You should set
this option before any tasks or resources are created. - Hours Per Week
This option defines the week unit
to be a certain number of hours. This option is important because the week unit
itself is not a concrete number in many business applications. You should set
this option before any tasks or resources are created. NOTE: The value of Hours Per Day and Hours Per Week should not be
changed after you begin creating tasks and resources because fractions of Days
and Weeks can result. Additionally, you will see changes in the way your plan is scheduled - Example
You work a standard 40 hours/week.
Your initial Hours Per Day is 8.
If you were to create a task of 1
day long, and then assign a resource to it, Microsoft Project consults the
Hours Per Day option to calculate how much work the resource should be assigned
(in this case 8 hours).
If you were to change the Hours Per Day
option to 6 hours, the resulting duration would be 1.33 days. This behavior
occurs because when you change the option you do not change the assignment on
the tasks. The resource is still working 8 hours on this task. In other words,
8 hours divided by 6 hours per day equals 1.3333 days duration.
REFERENCES For additional information, please see the following
article in the Microsoft Knowledge Base: 45695 Setting calendar working hours for evening/night shift
in Project In Microsoft Project online Help, see the following topics: - Calendar
- Change Working Time
- Assigning Calendars
Modification Type: | Major | Last Reviewed: | 5/3/2006 |
---|
Keywords: | kbhowto kbusage KB143254 |
---|
|