PRJ: Work Field in Team Assign Form Contains Duration Data (142922)
The information in this article applies to:
- Microsoft Project 98 for Windows
- Microsoft Project for Windows 95 4.1
- Microsoft Project for Windows 95 4.1a
This article was previously published under Q142922 SYMPTOMS
In the TeamAssign form sent to resources, the column labeled Work actually
contains Duration values. When a resource receives the form, the column
named Work will contain the resource Work for that task.
WORKAROUND
There is no workaround for this behavior.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
Modification Type: | Major | Last Reviewed: | 10/7/2003 |
---|
Keywords: | kbpending kbprb kbusage KB142922 |
---|
|