PRJ: Work Field in Team Assign Form Contains Duration Data (142922)



The information in this article applies to:

  • Microsoft Project 98 for Windows
  • Microsoft Project for Windows 95 4.1
  • Microsoft Project for Windows 95 4.1a

This article was previously published under Q142922

SYMPTOMS

In the TeamAssign form sent to resources, the column labeled Work actually contains Duration values. When a resource receives the form, the column named Work will contain the resource Work for that task.

WORKAROUND

There is no workaround for this behavior.

STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

Modification Type:MajorLast Reviewed:10/7/2003