PRJ: Deleting Base Calendar Causes General Protection (GP) Fault (137548)



The information in this article applies to:

  • Microsoft Project 98 for Windows
  • Microsoft Project for Windows 4.0

This article was previously published under Q137548

SYMPTOMS

After you delete a custom base calendar, you may receive the following error message:
WINPROJ4 caused a General Protection Fault in module WINPROJ.EXE at 0003:02A1

CAUSE

This problem occurs under the following conditions:

  • The base calendar is deleted through the Organizer

    -and-

  • The Resource Graph is the active view

    -and-

  • The resource that is viewed in the graph uses the base calendar that was deleted
NOTE: If the Resource Graph is formatted to display peak units, the GP fault does not occur.

WORKAROUND

To work around this problem, before you delete the base calendar, either apply a different view or format the Resource Graph to display peak units.

MORE INFORMATION


Modification Type:MajorLast Reviewed:10/7/2003
Keywords:kbbug kbfix KB137548