PRJ: Deleting Base Calendar Causes General Protection (GP) Fault (137548)
The information in this article applies to:
- Microsoft Project 98 for Windows
- Microsoft Project for Windows 4.0
This article was previously published under Q137548 SYMPTOMS
After you delete a custom base calendar, you may receive the following
error message:
WINPROJ4 caused a General Protection Fault in module WINPROJ.EXE at 0003:02A1
CAUSE
This problem occurs under the following conditions:
- The base calendar is deleted through the Organizer
- The Resource Graph is the active view
- The resource that is viewed in the graph uses the base calendar that
was deleted
NOTE: If the Resource Graph is formatted to display peak units, the GP fault does not occur.
WORKAROUND
To work around this problem, before you delete the base calendar, either
apply a different view or format the Resource Graph to display peak units.
MORE INFORMATION
Modification Type: | Major | Last Reviewed: | 10/7/2003 |
---|
Keywords: | kbbug kbfix KB137548 |
---|
|