PRJ: Subproject Task Appears To Be Calculated Incorrectly (112783)
The information in this article applies to:
- Microsoft Project for Windows 95 4.1
- Microsoft Project for Windows 95 4.1a
- Microsoft Project for Windows 3.0
- Microsoft Project for Windows 3.0a
- Microsoft Project for Windows 4.0
- Microsoft Project for the Macintosh 3.0
- Microsoft Project for the Macintosh 4.0
This article was previously published under Q112783 SYMPTOMS
When you link projects in a master-subproject relationship and the master
and subproject use different calendars, the start date and the duration are
calculated from the master file's calendar, but the finish date is rolled
up from the subproject file's calendar.
CAUSE
These different calendars are used to ensure that the master project and
the subproject have the same start and finish dates.
REFERENCES
"User's Reference," version 3.0, pages 488-498
Modification Type: | Major | Last Reviewed: | 11/25/2003 |
---|
Keywords: | kbprb KB112783 |
---|
|